Under the blazing sun, the noisy project site, all kinds of large machinery in orderly operation. Not far away, a few brand new kitchen cases, a few stacks of white tableware, and the scene seems out of place. Hundreds of meters apart, you can smell the fragrance of food. When we got closer, it turned out to be the crispy roasted suckling pig shining with the amount of oil. People wearing all kinds of helmets scrambled to taste the food and share this wonderful moment. Among the delighted crowd, there was the figure of Xuehao Yan, an after-sales engineer of EBICO.
The scene above took place at the construction site of the third runway project at Hong Kong International Airport, celebrating the successful trial laying of the asphalt concrete base for the main runway! Hong Kong International Airport, one of the busiest airports in the world, has expanded its existing two-runway system into a three-runway system in order to consolidate and strengthen its position as an international aviation hub. China Power Construction Group was contracted for the runway construction project, and EBICO participated as the appointed burner supplier for the asphalt mixing plant.
The concrete base trial paving operation, located on the east side of the runway, the test plot was 50 meters long and 30 meters wide, with a total area of 1,500 square meters. A total of 300 tons of asphalt concrete was paved, with four pavers jointly paving at the same time, a magnificent scene.
The 4000 asphalt mixing plant used for the airport pavement will be the largest asphalt concrete mixing and production system in HKSAR with the largest production capacity, largest investment and highest environmental standards. The EBS2500 asphalt mixing plant burner was selected by the EBICO team after considering various factors. This burner is suitable for light oil as fuel, with high combustion efficiency, low energy consumption, electronic intelligent proportioning, high rainproof, dustproof and explosion-proof level, which is an excellent burner product tested by the road base market.
To ensure the smooth progress of the trial paving project, Xuehao Yan insisted on squatting at the project site and working closely with the cooperative unit. In the process of producing asphalt, Yan Xuehao was calm and composed, carefully investigating and debugging on site, tracking the operation of the system in real time. Xuehao Yan will continue to stay at the runway project site to complete the unfinished mission.
This is not the first "encounter" between EBICO and Hong Kong, as early as a few years ago, during the construction of the "world's largest cross-sea bridge" - Hong Kong-Zhuhai-Macao Bridge, EBICO has already "met" with Hong Kong. "The Hong Kong-Zhuhai-Macao Bridge Before the bridge was opened to traffic, EBICO burners participated in the entire asphalt paving construction. The EBS-D asphalt mixing plant low nitrogen burner, which returned from the expedition, was successfully awarded the "Outstanding Product in Construction Machinery Industry to Celebrate the 70th Anniversary of the Founding of New China".
Recently, EBICO is nearing the end of its low-nitrogen transformation of the boiler burner of Changsha Wahaha Hengfeng Food Co., LTD., which is currently awaiting acceptance....
EBICO successfully won the low-nitrogen transformation project of two 6-ton steam boilers and two 20-ton steam boilers of Chengdu Aircraft Industrial (Group) Co., Ltd, and the production, installation and debugging of burners have been completed successfully....
Zhejiang Dushan Energy Co., Ltd., an important sign of the upstream industrial chain extension of xinfengming group, recently launched the PTA project with an annual output of 2.2 million tons and invited bids. The design concept of "safety, energy saving, environmental protection and intelligence" of EBICO burner coincides with the PTA production technology of Dushan energy, which lays a good foundation for the cooperation between the two sides....