Start up operation of burner

Start up operation of burner
Jul 14, 2020 Category: Technology Category Page Views: 73 Author: EBICO Burner
  1. Before commissioning the newly installed furnace body, it shall carefully test whether the gas and pressure meet the requirements of the burner; Check whether the testing instrument on the air supply pipeline is normal and whether the valve of the pipeline is open and closed normally, and whether it is convenient for use and testing in the future.

 

  1. For newly installed pipelines, carefully check the installation reliability and sealing of all pipelines.

 

  1. Users using separate gasification stations should ensure that the air supply quantity and gas supply parameters meet the requirements of safe combustion.

 

  1. Operators should read the operating instructions carefully and master the knowledge and methods of safe operation.

 

  1. Check whether the gas valve is open before starting each time, otherwise the burner will not work (and will not alarm).

 

  1. Start the "Run" button on the control. At this time, the digital display table will show the current temperature of water discharge, return and smoke exhaust of the furnace.

 

  1. After the delay of the boiler controller is about 1 minute, the relay of the burner is controlled to suck in, and the burner fan works for about 45 seconds to prepurge; If the burner fan does not work and does not alarm, check whether the low gas pressure switch is protected; Check whether the outlet temperature of boiler water meets the working requirements of boiler controller temperature parameters, that is, whether the outlet water temperature is lower than the set temperature.

 

  1. After the pre-purge of the burner, the damper is closed for ignition, the yellow light of the burner controller flashes and the ignition transformer discharges. About 2-3 seconds later, the gas solenoid valve is energized and opens.

 

  1. When the combustion controller receives signals that are not favorable to combustion (such as failed ignition, unstable air pressure, circuit problem, etc.), the combustion controller will immediately turn off the gas and issue an alarm signal.

 

  1. If the combustion controller alarms, it must be manually reset by the operator after the fault is solved before it can continue to work.

 

  1. For the operation of the whole equipment, operators should refer to the furnace safety operation rules and production process requirements for operation.

 

  1. When the control temperature needs to be adjusted according to the production process requirements, the operator should refer to the intelligent NUMERICAL control table manual for adjustment.

 

Burner startup

EBICO Burner answers the Start up operation of burner for you, to learn about the FAQ of EBICO Burner Technology Category. You can also learn more about other Technology Category FAQ about the EBICO Burner.
Need more information about EBICO please contact us
Need help?
Latest FAQ
More
Latest News
More
Sep 24, 2024

EBICO will attend Thailand's Premier Power Generation & Electric Exhibition...

Sep 26, 2023

How a bowl of Baixiang good noodles is born? About 1.8 million years ago, humans learned to cook food with purposeful control of fire. The use of fire has made unprecedented progress in human health and life, and Darwin also called cooking the most important invention of mankind after language....

Burner Products
Based on the experience of optimization and integration of combustion technology resources in Europe, we have achieved a safe, energy-saving and environmentally friendly burner that can be adapted to all thermal equipment.
Innovation
EBICO's attitude of pursuing excellence and continuous improvement promotes the innovation of burner products in safety, energy saving, environmental protection and intelligence.
CSR
CSR
EBICO has always established a positive relationship with the environment, economy and society in order to fulfill its responsibilities as an enterprise.
Focus on burners and equipment to lead the global thermal industry.
欧保(中国)环境工程股份有限公司版权所有 苏ICP备20014131号-1
Online
Email
Inquire